When snowfall exceeds two inches, an order for snow removal (private streets, driveways, and sidewalks) will be placed. When possible, please have private streets and driveways clear of vehicles for more effective services.
Painting is completed in the following 5 phases.
Phase 1: 12100, 12104, 12108, 12112, 12116, 12120, 12124, 12128, 12132, and 12136 Grant St; 9519 and 9523 W, 121st Terr
Phase 2: 12140 Grant St; 9502, 9506, 9510, 9514, 9518, 9515, 9511, 9507, 9503, and 9501 W. 121st Terr
Phase 3: 9502, 9504, 9506, 9510, 9512, 9514, and 9511 W, 122nd St; 12202, 12206, 12208, 12212, and 12214 Grant Lane
Phase 4: 12218, 12220, 12224, and 12226 Grant Lane; 9507, 9509, 9513, 9517, 9521, and 9523 W. 122nd Terr
Phase 5: 9505 W. 122nd St; 12201, 12205, 12207, 12209, 12213, 12217, 12219, and 12223 Grant Lane; and 9508 w. 122nd Terr
House Trim Painting:
Phase 1: Completed 2021
Phase 2: Completed 2022
Phase 3: Completed 2023
Phase 4: 2024
Phase 5: 2025
Tentative Stucco and Trim Painting Schedule:
Phase 1: 2026
Phase 2: 2027
Phase 3: 2028
Phase 4: 2029
Phase 5: 2030
Owners are responsible for repair of wood rot. It is important that all wood rot be repaired prior to trim painting. Owners may obtain paint for touch up of repaired wood from Architecture Director.
Owners are also responsible for repair of stucco. Owners may obtain paint for touch up of repaired wood from Architecture Director.